May 31, Anton Nozdrin). Today Ilsur Metshin, the Mayor of Kazan, estimated the
quality of major repairs, which took place in the house №32 on Otradnaya Street
for the first time in 50 years. The head of the city also got acquainted with
the progress of the works, which began as part of the complex improvement of
the yard territory of the adjacent houses, and spoke with the residents. This
year, the overhaul of residential buildings will affect more than 200 thousand
Kazan citizens.
Repair of
drainage systems, roofing, entrances, facade, cold water supply systems, and
other types of work have been done in a house, built in 1959, where 53
residents live. Firdaus Bayazitova, the head of the house, told the Mayor that
she has been living in this house for 50 years and the building has never been
repaired during this time. “This year everything was done: replacement of
sewerage, batteries in apartments, change of wiring. Everything was done just
fine”, shared F. Bayazitova. According to her, the house was in a terrible
state before the repair began and she thanked the builders for the qualitative
work. “We did not believe that the house would be renovated like that. We
expected that there would be a good repair but it turned out great. Now all the
neighbors envy us”, said the head of the house.
I. Metshin
told the resident that the overhaul was not only in their house. “This year we
will make 242 houses. And all will be of the same quality. The repair will
affect more than 200 thousand Kazan citizens”, said the Mayor. The repair work
has already begun in 200 houses. The Mayor also added that 2200 houses with
more than half a million people have been thoroughly renovated over the 8 years
of the program's existence. “624 thousand Kazan citizens received new
conditions after the overhaul”, marked I. Metshin.
The head of
the city visited one of the apartments in the house. Svetlana Nikandrova, its
owner, told that new cast-iron batteries were installed in each room, kitchen,
and bathroom. “Everything was done quickly, without downtime. The workers are
fine professionals”, noted the resident and thanked Ilsur Metshin and the
administration of the district for the qualitative repairs carried out in the
house.
S.
Nikandrova noted in a conversation with the Mayor that all the repair work was
preliminarily discussed with the residents and the wishes of the tenants were
taken into account. “It is good that contractors have learned to work in
dialogue with residents, to listen to their wishes and problems. We are glad
that you give such an assessment to the builders and the administration of the
district”, said the Mayor of Kazan.
In addition
to the overhaul of the residential building, the work is planned in the yards
of houses №32 on Otradnaya Street and №27, 29 on Daurskaya Street as part of
the program “Bringing the yard territories into the normative state”.
Currently, the preparatory works are carrying out there: clearing and leveling
the sites, planning the territory. As a result of improvement, the roads will
be renovated, and benches and a playground will appear according to the
project.
Residents
of nearby houses appealed to the Mayor with a request to make a football field
in the yard. As citizens said, they always came here to play football in their
childhood and now there is no suitable field in the district for young
athletes. I. Metshin instructed Rustem Gafarov, the head of the Sovetsky
district’s administration, to work out the question of installing a universal
sports ground in the yard.
Iskander
Giniyatullin, the deputy head of the Executive Committee and the chairman of
the Housing and Communal Services Committee, Igor Kulyazhev, the deputy head of
the Executive Committee and the chairman of the Committee for External
Improvement, Fargat Giniyatov, the director of the management company
“Tankodrom”, Bulat Ahmetgarayev, the director of the contractor OOO “Portal”,
and others also took part in the event.
Out of the
242 Kazan houses, which are planned to be repaired this year, it is planned to
perform the whole complex of work in 130 houses, 141 lifts will be replaced in
45 houses, weather control devices will be installed in 114 houses. The works
are started in 200 houses, the fulfillment is 41%. The complex repair will be
realized in 117 houses. This year it is planned to equip 180 adjacent
territories and 30 intra-quarter passages on a total area of over 230,000
square meters.